    The planning fallacy

    holds up

    Researchers have tested this many times, in different places, over many years, and they keep finding the same result. This one is safe to trust.

    A group of psychology students were asked a simple question: when will you finish your thesis? They gave their best honest estimate, on average about 34 days. Then the researchers waited and measured. The real average was 56 days. Fewer than a third finished by the date they had predicted, and many ran far over. The next part makes it more than a story about students. The same students were also asked to estimate how long other people would take on similar projects, and those estimates were far more accurate. When they judged someone else, they instinctively used the track record, how these things usually go. When they judged themselves, they used the plan, the smooth version in their head where nothing goes wrong. The plan is always optimistic, because the plan does not include the interruptions it cannot foresee.

    You predict your own timelines badly and other people's timelines well, and the reason is the method you use for each. For yourself you imagine the ideal run. For others you remember how it actually tends to go. So the fix is mechanical: when you estimate your own next project, stop imagining it, and instead look at how long your last three similar projects really took. That number, the boring historical one, is a better predictor than any plan you can build, because it already contains the delays you are about to forget again. Naming exactly when and where you will start is a separate lever and a strong one, which is implementation intentions.

    Source: Buehler, Griffin and Ross, Exploring the planning fallacy, Journal of Personality and Social Psychology, 1994. On estimating from comparable projects instead: Flyvbjerg and Gardner, How Big Things Get Done, 2023.

    The book, if you want to go further

    How Big Things Get Done

    Flyvbjerg and Gardner, 2023

    Built on a database of sixteen thousand projects, of which fewer than one in ten came in on budget and on time. Its method is to stop estimating from inside the project and look instead at what comparable projects actually took.

    The Saturday letters

    Every Saturday, one idea worth your time, with an honest account of how far the evidence really goes and where it stops. Free, a few minutes to read, and it leaves you with questions rather than instructions.

    You will get one email asking you to confirm this address. Nothing arrives until you click it.

    Draw your own card. It does not take long, and it rewards taking your time.